1.1 Roofing requires substantial preplanning early in the project. Specifically check the following items:
- roof pitch (for selection of sheet profile/s)
- roof selection specified vs. actual required including protection of the underside of sheets when metal soffits
- are exposed or semi exposed. This can affect the warranty and may also affect the selection of the framing in
- semi exposed areas and marine environments.
- expansion joints and materials bridging the joints. (structural steel may be influenced)
- gutter/downpipe designs, size and selection including penetrations in steel/precast etc
- roof penetration locations and flashing systems (support for soakers etc)
- roof access systems
1.2 Review this policy for more information but be aware that prior to structural works, the above items must be considered and designed correctly prior to commencement of works.